Bullet train debuts on new railway in Tibet

0 Comment(s)Print E-mail Xinhua, June 26, 2021
Aerial photo taken on June 16, 2021 shows a Fuxing bullet train running on the Lhasa-Nyingchi railway over the Yarlung Zangbo River during a trial operation in southwest China's Tibet Autonomous Region. The first electrified railway in southwest China's Tibet Autonomous Region opened on June 25, 2021, linking regional capital Lhasa with the city of Nyingchi, as Fuxing bullet trains enter official operation on the plateau region. With a length of 435 kilometers and a designed speed of 160 kilometers per hour, the new railway is a single-line electrified railway. It is the first time that Fuxing bullet trains, which were independently developed by China, are transporting passengers in Tibet. The Fuxing bullet train series have been operating in all provincial-level regions of the Chinese mainland. (Xinhua/Purbu Zhaxi)

The first electrified railway in southwest China's Tibet Autonomous Region opened Friday morning, linking regional capital Lhasa with the city of Nyingchi, as "Fuxing" bullet trains enter official operation on the plateau region.

With a length of 435 km and a designed speed of 160 km per hour, the new railway is a single-line electrified railway. There are currently nine stations in the cities of Lhasa, Shannan and Nyingchi that can handle passenger and freight transportation.

The newly opened Lhasa-Nyingchi railway has provided southeast Tibet with access to railway services for the first time in history.

Compared to roads, the Lhasa-Nyingchi railway reduces the travel time from Lhasa to Nyingchi from 5 hours to approximately 3.5 hours, and cuts the travel time from Shannan to Nyingchi from 6 hours to approximately 2 hours.

It is the first time that Fuxing bullet trains, which were independently developed by China, are transporting passengers in Tibet. The Fuxing bullet train series have been operating in all provincial-level regions of the Chinese mainland.

The Fuxing trains in service now have a speed range of 160 km to 350 km per hour, a notable feat in China's railway technological innovation.

The construction of the railway began in March 2015. More than 130,000 workers have been laboring in the mountains to build the railway, 90 percent of which is more than 3,000 meters above the sea level.

The rail line passes through 47 tunnels and 121 bridges, and crosses the Yarlung Zangbo River 16 times. Tunnels and bridges account for approximately 75 percent of the total length of the railway, which meant challenges for construction workers and provided valuable experience for the construction of railways on plateaus.

The railway's annual freight transport capacity of 10 million tonnes provides strong support for the flow of goods, which will promote economic development and improve people's lives.

1   2   3   4   5   6   7   8   9   10   >  


Print E-mail Bookmark and Share

Go to Forum >>0 Comment(s)

No comments.

Add your comments...

  • User Name Required
  • Your Comment
  • Enter the words you see:    
    Racist, abusive and off-topic comments may be removed by the moderator.
Send your storiesGet more from China.org.cnMobileRSSNewsletter