Workers with the Three Gorges Project will face three major new
tasks after the diversion channel, built for the passage of ships
during the second-phase of construction, is fully dammed on
November 6.
Lu
Youmei, general manager of the China Yangtze River Three Gorges
Project Development Corporation, said, "A new construction peak
will start when the natural flow of the mighty Yangtze is stopped
near the dam site, and the project will begin to play part of its
role."
Workers will then be required to build over the next eight months
the final 665-meter-long section of the 2,309-meter-long and
185-meter-high dam, workshops for 12 generators on the southern
bank of the Yangtze, and the vertical ship lift on the northern
bank.
By
June next year, the Three Gorges Dam will begin to store water to a
level of 135 meters and the first four generators will start power
operation.
A
total of 5.5 billion kw hours of electricity will be generated in
2003 alone. Power will be transmitted to the provinces of Hubei,
Henan, Hunan, Jiangxi, Jiangsu, Zhejiang, Anhui, Guangdong and to
Shanghai Municipality.
The first two phases of the project were concentrated chiefly along
the northern bank. The mainstream of the Yangtze, China's longest
river, was first dammed in November 1997.
The Three Gorges Project has been designed to harness the Yangtze
in the aspects of flood control, power generation and
navigation.
Construction began in 1993 and is expected to be completed in 2009,
when 26 power-generating units with a combined capacity of 18.2
million kilowatts will go into operation. The permanent locks will
also be able to accommodate ships of more than 10,000 DWT
(deadweight tonnage).
The entire project is estimated to cost 180 billion yuan (US$21.7
billion ).
(People's Daily
November 5, 2002)